Rinnai 2402 Specifications Page 28

  • Download
  • Add to my manuals
  • Print
  • Page
    / 48
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 27
Model 2402www.rinnaiamerica.com 2 8
INSTALLER’S INSTALLATION INSTRUCTIONS
Gas Piping Notes
1) A manual gas control valve must be placed upon the gas inlet connection to the
Continuum 2402 before it is connected to the gas line. A union can be used on the
connection of the Continuum for the future servicing or disconnection of the unit.
2) Check the type of gas and the gas inlet pressure before connecting the Continuum
2402. If the Continuum 2402 is not of the gas type that the building is supplied
with, DO NOT connect the water heater. Contact the dealer for the proper unit to
match the gas type.
3) Minimum and Maximum Gas pressures are listed below:
* Minimum value is for input adjustment
Natural Gas: Minimum 7" WC Propane Gas: Minimum 10"WC
Maximum 10.5" WC Maximum 14" WC
WARNING: Conversion of this unit from natural gas to propane or propane to
natural gas CANNOT be done in the field.
4) After completion of gas pipe connections, all joints including the heater must be
checked for gas-tightness by means of leak detector solution, soap and water, or an
equivalent nonflammable solution, as applicable. Caution: Since some leak test
solutions, including soap and water, may cause corrosion or stress cracking, the
piping must be rinsed with water after testing, unless it has been determined that
the leak solution is non-corrosive.
5) The Continuum 2402 must be leak tested before it is placed into operation.
6) The Continuum 2402 and its individual shut-off valve must be disconnected from the
gas supply piping system when pressure testing of the gas supply piping system at
test pressures equal to or greater than 1/2 psi.
7) Always use approved connectors to connect the unit to the gas line. Always purge
the gas line of any debris before connection to the water heater.
8) The Continuum 2402 must be isolated from the gas supply piping system by closing
it's individual manual shutoff valve during any pressure testing of the gas supply
piping system at test pressures less than 1/2 psi.
9) The Continuum 2402's Installation location must provide adequate Combustion and
Ventilation airflow.
Page view 27
1 2 ... 23 24 25 26 27 28 29 30 31 32 33 ... 47 48

Comments to this Manuals

No comments